Bore logs
5 logs from crews in your region
County Line water bore
County Line Rd & 41st · Broken Arrow, OK
WaterClay720 ft18 ft
Pretreat the water — pH under 8.5 and the clay stops swelling. Swap to a fluted reamer, not a fly cutter.
Dale Prichard · Redline Underground2
Elm St highway crossing
1204 Elm St · Tulsa, OK
FiberRocky / cobble480 ft14 ft
Shoot the walkover grid before the shift starts. Drop to 6ft/min through the shelf and bump the polymer; the shelf is only ~30ft wide.
Dale Prichard · Redline Underground2
Harvard Ave sewer casing
3100 S Harvard Ave · Tulsa, OK
SewerSolid rock640 ft22 ft
Budget double the pilot time and run wireline — walkover is useless at that depth here.
Ken Ostrowski · Ironhead Directional1
Riverbend gas main tie-in
88 Riverbend Rd · Tulsa, OK
GasWet sand310 ft9 ft
Keep annular pressure low near the bank and pre-ream in two passes. Bring extra straw wattle — the inspector will ask.
Rae Whitfield · Cottonwood Boring Co.1
Mingo Rd primary electric
5500 S Mingo Rd · Tulsa, OK
ElectricSandy loam205 ft7 ft
Every yard on this stretch has private irrigation. Pothole at 3ft even when the locate is clear.
Tyler Nunn · Bluestem Utility0